ok heres what i got together so far.all the panels were put together by me the last couple days and today i started putting things together.
Everything was put together with dowels and glue the way i showed the other nite.you can change the mesurements to suit your needs but heres what mine were for reference.
The bottom wich was put together with 1" by 4" by 6' boards and then cut down to 20 3/4" by 34"
Sides: 20" by 36"
Sub floor: 2 pieces 1" by 6" by 20 5/8"
1 piece 1" by 6 " by 35 1/2 "
What i did was attach the sides to the bottom keeping the bottom outside edge flush,and in line with the outside edge of the sides!
I used 3 dowels on each side to attach the sides to the bottom.
Then to make your sub floor to lift the bottom of the cab up and give you an air space under the floor (in this case 5 inchs) i took the two shorter pieces of the sub floor,and attached them where the bottom ,and side come together. when you put your dowels in to make sub floor you will be going into the floor itself not the sides.
After the side two are on do the same to the front of the cab with the remaining piece.
You can see some of the dowels still sticking out.i cut them flush and sand them smooth when there dry.
The last one shows a better view of the way the sub floor gets the main floor up off the ground.dont short yourself on height here this is where fresh air will be coming from.
The other thing i wanted to touch on is the back is finished and ready to be put on however in this case the back will be the last thing that goes on.
You will understand more as to why tomorrow.i have a way of locking the cab that needs me to get into the back untill its working proper.
Its really so simple its dumb,but ill tell ya.everytime i watch someone try and figure out how to do it it just amazes me that folks forget to look at the obvious.that,and if your buddies are over its comicial as hell lmao